On 22 July 2011 Nauru Ocean Resources Inc. (NORI), a wholly-owned subsidiary of The Metals Company, was granted a polymetallic nodule exploration contract concerning 4 areas in the Clarion Clipperton Zone (CCZ), sponsored by the government of the Republic of Nauru.

An environmental impact statement from NORI regarding its plans to carry out testing of a polymetallic nodule collector system components, in the NORI-D Contract Area of the eastern Clarion-Clipperton Zone was submitted on 30 July 2021, with updates and resubmission on 1 March 2022. A Environmental Management and Monitoring Plan (EMMP) was submitted on 2 May 2022. The Legal and Technical Commission (LTC) made requests concerning the detail of the EIA in March 2022 and both the EIA and EMMP in July 2022 (ISBA/27/C/16/Add.1, paras. 42-47):
The Commission therefore decided that it was unable to recommend to the Secretary-General of the Authority that the environmental impact statement be included in the programme of activities of NORI.
ISBA/27/C/16/Add.1, para. 46.
In August 2022 the LTC concluded its review of the additional information provided by NORI on 1 August 2022 and recommended to the Secretary-General of ISA that the completed EIS be incorporated into the programme of NORI’s activities under its exploration contract with ISA. On 5 September 2022, the Secretary-General notified the contractor of the recommendation of the LTC (ISA Press Release) and the pilot collection system trials in the NORI-D Exploration Area (see below) are scheduled to begin in September 2022.